CL-2026-038

RFP: Organic Material Removal & Disposal

The Town of Mount Pleasant is seeking contractor proposals for organic material removal and disposal work at the Clay Bird Lane site. Two addenda followed: Addendum No. 1 extended the deadline, and Addendum No. 2 added two special notices without extending it further. This page is a pointer, not a substitute — read the actual solicitation documents before relying on anything here.

Read the documents

Scope as stated in the RFP

  • Use of heavy equipment, trailers and related equipment for the processing, removal and disposal of approximately 25,000 cubic yards of processed organic material in different stages of processing into mulch.
  • The contractor must submit a plan detailing the work and the time required to complete it.
  • Work in the mulch site area is limited to 7:00 AM to 6:00 PM; trucks leaving the site are restricted to 8:30 AM to 4:30 PM.

Key dates

  • Proposal deadline as originally issued: Monday, August 3, 2026 at 11:00 AM (local time). This was later extended; see Addendum No. 1.

Full scope of work, submission instructions, and compliance requirements are in the RFP documents linked above.

Contact

Engineering Department — 914-742-2317